Alto Rabagão Dam
Alto Rabagão Dam (Portuguese: Barragem do Alto Rabagão) is a concrete dam on the Rabagão River, a left tributary of the Cávado River. It is located in Peneda-Gerês National Park, in the municipality Montalegre, in Vila Real District, Portugal.
Alto Rabagão Dam | |
---|---|
Location of Alto Rabagão Dam in Portugal | |
Official name | Barragem do Alto Rabagão |
Location | municipality Montalegre, Vila Real District, Portugal |
Coordinates | 41°44′22.2″N 7°51′27.4″W |
Purpose | Power |
Status | Operational |
Construction began | 1957 |
Opening date | 1964 |
Owner(s) | Companhia Portuguesa de Produção de Electricidade |
Dam and spillways | |
Type of dam | Concrete arch and gravity dam |
Impounds | Rabagão River |
Height (foundation) | 94 m (308 ft) |
Length | 1,970 m (6,460 ft) |
Elevation at crest | 880 m (2,890 ft) |
Dam volume | 1,117,000 m3 (39,400,000 cu ft) |
Spillway type | Over the dam |
Spillway capacity | 500 m3 (18,000 cu ft) |
Reservoir | |
Total capacity | 568,690,000 m3 (461,040 acre⋅ft) |
Active capacity | 557,920,000 m3 (452,310 acre⋅ft) |
Surface area | 22.12 km2 (8.54 sq mi) |
Normal elevation | 880 m (2,890 ft) |
Alto Rabagão Power Plant | |
Coordinates | 41°42′37.13″N 7°55′0.70″W |
Operator(s) | Energias de Portugal |
Commission date | 1964 |
Type | Pumped-storage |
Hydraulic head | 185 m (607 ft) (max) |
Turbines | 2 x 36.75 MW reversible Francis-type |
Installed capacity | 68 MW |
Annual generation | 85.2 GWh |
Construction of the dam began in 1957. The dam was completed in 1964. It is owned by Companhia Portuguesa de Produção de Electricidade (CPPE). The dam is used for power production.[1]
Dam
Alto Rabagão Dam is a 94 m tall (height above foundation) and 1,970 m long concrete dam, which is composed of an arch dam in the center and gravity dams on both sides. Its crest altitude is 880 m. The volume of the dam is 1,117,000 m³. The dam contains a crest spillway with 2 gates (maximum discharge 500 m³/s) and a bottom outlet (maximum discharge 360 m³/s).[1]
Reservoir
At full reservoir level of 880 m (maximum flood level of 880.1 m) the reservoir of the dam has a surface area of 22.12 km² and its total capacity is 568.69 mio. m³. Its active capacity is 557.92 (550[2][3] or 550.1[4]) mio. m³. Minimum operating level is 829 m.[1] With the 550.1 mio. m³ water 973.1 GWh can be produced.[4]
Power plant
The pumped-storage hydroelectric power plant went operational in 1964. It is owned by CPPE, but operated by EDP.[5] The plant has a nameplate capacity of 68[1][4][5] (72)[3] MW. Its average annual generation is 85.2[4] (83[2] 95[3] or 97[1][5]) GWh.
The power station is located downstream and contains 2 reversible Francis turbine-generators with 36.75 MW (45 MVA), each in an underground powerhouse. The turbine rotation is 428 rpm. The minimum hydraulic head is 129 m, the maximum 185 m. Maximum flow per turbine is 25.7 m³/s. When pumping, each of the pumps has a maximum energy consumption of 31.7 MW and can pump 18 m³/s.[4] The pumps are operated independently of the Francis turbines.[2]
As lower reservoir for Alto Rabagão the reservoir of Venda Nova Dam is used.[2]
References
- "ALTO RABAGÃO DAM". APA Barragens de Portugal. Retrieved 2015-02-15.
- "DECLARAÇÃO AMBIENTAL 2012" (PDF) (in Portuguese). Energias de Portugal. p. 18-20 (16-18). Archived from the original (PDF) on 2014-11-03. Retrieved 2015-02-15.
- "Hidroelectricidade em Portugal memória e desafio" (PDF) (in Portuguese). Rede Eléctrica Nacional, S.A. p. 29 (27). Retrieved 2015-02-15.
- "Alto Rabagão Informação Técnica" (in Portuguese). Energias de Portugal. Archived from the original on 2014-12-27. Retrieved 2015-02-15.
- "Alto Rabagao Hydroelectric Power Plant Portugal". Global Energy Observatory. Retrieved 2015-02-15.
Wikimedia Commons has media related to Alto Rabagão Dam. |