North–South Line (Jakarta MRT)

The North–South line is a rapid transit line of the Jakarta MRT. Coloured red on the map, the line is currently 15.7 km long and serves 13 stations. It is the first line of the Jakarta MRT.

North–South Line
Overview
StatusOperational (Phase 1)
Under Construction (Phase 2A)
OwnerMinistry of Transportation
LocaleJakarta, Indonesia
TerminiLebak Bulus
Bundaran HI
Stations13
Service
TypeRapid transit
SystemJakarta MRT
Services1
Operator(s)PT MRT Jakarta
Depot(s)Lebak Bulus
Ancol Barat (future)
Rolling stock16 six-car MRTJ 1000 series trainsets
History
Opened24 March 2019 (2019-03-24)
Technical
Line length15.7 km (9.8 mi)
CharacterElevated
Underground
Track gauge1,067 mm (3 ft 6 in)
Electrification1,500 V DC overhead catenary
Operating speedlimit of 100 km/h (62 mph)
Route map

↑ Phase 2 
 
Ancol Barat Depot
Ancol
Jakarta Inner Ring Road
Gunung Sahari
Mangga Dua
↑ Phase 2B
Kota
Glodok
Mangga Besar
Sawah Besar
Harmoni
Monas
Thamrin
 M2 
↑ Phase 2A: opening 2027
BHI
Bundaran HI
DKA
Dukuh Atas BNI
()
BNI City Sudirman
West Flood Canal
Dukuh Atas
STB
Setiabudi Astra
BNH
Bendungan Hilir
Jakarta Inner Ring Road
IST
Istora Mandiri
SNY
Senayan
SSM
ASEAN
BLM
Blok M BCA
BLA
Blok A
HJN
Haji Nawi
CPR
Cipete Raya
Jakarta Outer Ring Road
FTM
Fatmawati
LBB
Lebak Bulus Grab
Lebak Bulus Depot

History

Jakarta MRT underground section between Dukuh Atas station and Bundaran HI, in March 2018

Phase 1

A total of eight contracts were awarded.

  • CP 101 (Construction of Lebak Bulus Depot, Lebak Bulus station and related elevated works) awarded to Tokyu Corporation - Wijaya Karya consortium.
  • CP 102 (Construction of Cipete Raya and Fatmawati stations and related elevated works) awarded to Tokyu Corporation - Wijaya Karya consortium.
  • CP 103 (Construction of Haji Nawi, Blok A, Block M and ASEAN stations and related elevated works) awarded to Obayashi Corporation - Shimizu Corporation - PT Jaya Konstruksi JV.
  • CP 104 (Construction of Senayan and Istora stations and related tunnelling works awarded to Shimizu Corporation - Obayashi Corporation - PT Wijaya Karya - PT Jaya Konstruksi JV.
  • CP 105 (Construction of Bendungan Hilir and Senayan stations and related tunnelling works awarded to Shimizu Corporation - Obayashi Corporation - PT Wijaya Karya - PT Jaya Konstruksi JV.
  • CP 106 (Construction of Dukuh Atas and Bundaran HI stations and related tunnelling works awarded to Sumitomo Mitsui Construction Company - PT Hutama Karya consortium.
  • CP 107 (Construction of railway systems and trackworks) awarded to Metro One consortium.
  • CP 108 (Construction of rolling stock) awarded to Sumitomo Corporation - Nippon Sharyo consortium.

On 1 June 2013, the first three civil contracts for the 9.2 km (5.7 mi) underground section were signed. Three civil engineering contracts for the elevated section were signed in the third quarter of 2013. Construction work began in October 2013.[1]

Tunnelling was completed on 23 February 2017, meeting the target completion date.[2] By October 2017, the construction of both elevated and underground line sections were completed.[3]

Ahead of its official opening, a limited public trial run was conducted from 12 March 2019 to 23 March 2019. The official opening ceremony was held on 24 March 2019 by the Indonesian president, Joko Widodo.[4][5]

Phase 2

A total of eight contracts were put up.

  • CP 200 (Construction of underground electrical substation near Monas station) awarded to PT Trocon Indah Perkasa.
  • CP 201 (Construction of Thamrin and Monas stations and related tunnelling works) awarded to Shimizu Corporation - PT Adhi Karya JV.
  • CP 202 (Construction of Harmoni, Sawah Besar and Mangga Besar stations and related tunnelling works) awarded to Shimizu Corporation - PT Adhi Karya - MOC JV.
  • CP 203 (Construction of Glodok and Kota stations and related tunnelling works).
  • CP 204 (Construction of depot at Ancol Barat).
  • CP 205A (Construction of railway systems and trackworks from Bundaran HI to Mangga Besar stations) awarded to awarded to Shimizu Corporation - PT Adhi Karya - MOC JV.
  • CP 205B (Construction of railway systems and trackworks from Mangga Besar to Kota stations)
  • CP 206 (Construction of 12 sets of rolling stock).

Groundbreaking for Phase 2 was initially planned to begin on 19 December 2018. However, due to land acquisition issues, it was pushed back a month, to January 2019. On 30 January 2019, President Director of PT MRT Jakarta, William Sabandar announced that the groundbreaking ceremony is delayed again as the State Secretariat has yet to issue a land-use permit for the area near Medan Merdeka.[6]

The groundbreaking ceremony for Phase 2 was finally held on 24 March 2019. Advanced works began in June 2019 near the future Monas station.[7]Site works were originally planned to begin in March 2020. However, due to the COVID-19 pandemic, it was pushed back three months, to June 2020.[8]

Network

Jakarta MRT set 11 departing from Lebak Bulus station

Stations

Region Station Name Transfers/Notes
Phase 2B (planned)
North Jakarta Ancol Barat Future terminal station
Ancol
Mangga Dua
Phase 2A (under construction, fully operational by 2027)
West Jakarta Kota Future Phase 2A terminus

KRL Commuterline (planned at Jakarta Kota)

Intercity trains (planned at Jakarta Kota)

Transjakarta (planned at K1-20 Kota)

Glodok Transjakarta (planned at K1-19 Glodok)
Mangga Besar Transjakarta (planned at K1-17 Mangga Besar)
Central Jakarta Sawah Besar Transjakarta (planned at K1-16 Sawah Besar)
Harmoni Transjakarta (planned at K1-15 Harmoni)
Monas Transjakarta (planned at K1-14 Monas)
Thamrin  M2  Planned interchange station to  M2 

Transjakarta (planned at K1-12 Sarinah)

Phase 1
Central Jakarta Bundaran HI Phase 1 terminus

Transjakarta (K1-11 Bundaran HI)

Dukuh Atas BNI KRL Commuterline (at Sudirman)

Soekarno-Hatta Airport Rail Link (at BNI City)

Jakarta LRT (planned at Dukuh Atas)

 L2  Greater Jakarta LRT (planned at Dukuh Atas)

Transjakarta (K1-9 Dukuh Atas 1)

Transjakarta (K4-17 Dukuh Atas 2)

Transjakarta (planned at K6-20 Dukuh Atas 2)

Setiabudi Astra
Bendungan Hilir Transjakarta (K1-6 Bendungan Hilir)

Transjakarta (K9-15 Semanggi)

Istora Mandiri Transjakarta (K1-5 Polda Metro Jaya)
Senayan Transjakarta (K1-3 Bundaran Senayan)
South Jakarta ASEAN[9] Initially named 'Sisingamangaraja'

Transjakarta (K1-2 Masjid Agung)

Transjakarta (planned at K13-4 CSW)

Blok M BCA Transjakarta (K1-1 Blok M)
Blok A
Haji Nawi
Cipete Raya
Fatmawati
Lebak Bulus Grab Terminal station

Transjakarta (K8-1 Lebak Bulus)

References