Nysted Wind Farm
The Nysted Wind Farm (also known as Rødsand) is a Danish offshore wind farm close to the Rødsand sand bank near Lolland. Gravity base foundations are used rather than piles due to ice conditions.[3]
Nysted Wind Farm | |
---|---|
Country | Denmark |
Location | South of Lolland |
Coordinates | 54°33′0″N 11°42′36″E |
Status | Operational |
Commission date | 2003 |
Construction cost | about EUR 600 million |
Owner(s) | DONG Energy, PensionDanmark |
Wind farm | |
Type | |
Power generation | |
Units operational | 162 × 2.3 MW (Siemens) |
Make and model | Siemens Wind Power |
Nameplate capacity | 166 MW (Rødsand I) 207 MW (Rødsand II) 383MW total |
Annual net output | 1,370 GW·h[1][2] |
External links | |
Commons | Related media on Commons |
Rødsand I
Rødsand I was built in 2003, with 72 turbines and a total capacity of 166 MW, and was the largest in the world until 2007.[4] Annual production is some 570 GW·h, the equivalent to the electricity consumption of 140,000 Danish homes, which could save 500,000 tonnes of CO
2 emissions.[5] Turbines were installed by A2SEA.[6] It receives 45 øre per kW·h for the first 42,000 full-load hours, which is about 11 years.[7]
Rødsand I was out for 41⁄2 months in 2007 when the main transformer suffered a malfunction,[7] causing a production loss of 23 million DKK per month.[4]
In September 2010, DONG bought E.ON's 20% share and sold half of the entire project to pension fund PensionDanmark for 700 million kroner (€94 million / US$120 million) — almost half the DKK1,600 million cost.[1] Stadtwerke Lübeck also owns a share.[7]
As of 2013 it has an availability of 97 percent.[7]
Rødsand II
In 2010, a 207 MW extension of the existing wind farm was installed by E.ON at a stated cost of EUR450m[8] and a power purchase agreement at DKK 0.629 per kW·h (US$0.12/kW·h).[9] It was originally scheduled to be completed in 2011,[10] but installation happened faster than projected,[11] and on 15 July 2010, E.ON reported that all turbines had been installed and the majority were supplying power to the Danish grid.[12] On 3 August, E.ON reported that the wind farm was ready and went into operation, three months ahead of schedule.[13] Rødsand 2 was inaugurated on 12 October.[2]
In November 2013, local power company SEAS-NVE bought 80% of Rødsand 2 for a price of DKK 2.8 billion and thus valuating the wind farm at DKK 3.5 billion.[14]
See also
References
- Wittrup, Sanne. Pension fund becomes wind farm owner (in Danish) Ingeniøren, 9 September 2010. Retrieved: 17 April 2011.
- "Rødsand 2 wind farm online". The Copenhagen Post. 13 October 2010. Archived from the original on 16 October 2010. Retrieved 2010-10-14.
- Rødsand 1 4C . Retrieved: 31 July 2010.
- Sanne Wittrup. "Havvindmøller i Nysted lammet af transformerhavari" (in Danish) Ingeniøren, 31 July 2007. Accessed: 13 December 2013.
- "A2SEA presentation" (PDF). A2SEA. Export Promotion Denmark. 2005-04-12. Archived from the original (PDF) on 2011-07-19. Retrieved 2010-07-14.
- Sanne Wittrup. "Østersø-havmøllepark har leveret varen i ti år" (in Danish) Ingeniøren, 13 December 2013. Accessed: 13 December 2013.
- Rødsand 2 4C . Retrieved: 31 July 2010.
- Pia C. Jensen & Steen Hartvig Jacobsen. "Wind turbines in Denmark Archived 2013-10-23 at the Wayback Machine", page 26. Danish Energy Agency, November 2009. Accessed: 4 September 2013.
- Rødsand II Wind Farm, Denmark
- Rødsand 2 to finish ahead of schedule Maritime Danmark, 18 June 2010. Retrieved: 19 June 2010.
- E.ON completes turbine installation at Roedsand windfarm Offshore Shipping Online, 15 July 2010. Retrieved: 31 July 2010.
- Vindkraftparken Rødsand 2 er nu klar (Wind farm Rødsand 2 is now ready) Press release in Danish, 3 August 2010. Retrieved: 13 September 2010.
- Wittrup, Sanne. "Lokalt elselskab køber Rødsand havmøllepark i historisk milliardhandel" (in Danish) Ingeniøren, 13 November 2013. Accessed: 13 November 2013.