Orange Line (Bangkok)
The MRT Orange Line (Thai: รถไฟฟ้ามหานคร สายสีส้ม) is a rapid transit lines of the Mass Rapid Transit Authority of Thailand (MRTA) in the Bangkok Metropolitan Area, Thailand.
MRT Orange Line รถไฟฟ้ามหานคร สายสีส้ม | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Overview | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Status | Under Construction (Eastern Section) Bidding and Tendering (Western Extension) | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Owner | Mass Rapid Transit Authority of Thailand | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Locale | Bangkok, Thailand | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Termini | Bang Khun Non Yaek Rom Klao | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Stations | 29 17 (Under construction) 12 (planned) | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Service | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Type | Rapid transit | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
System | MRT | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
History | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Planned opening | 2024 (Eastern section) | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Technical | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Line length | 35.86 kilometers (22.28 mi) | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Track length | 22.57 kilometers (14.02 mi) (under construction) [1] | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Track gauge | 1,435 mm (4 ft 8 1⁄2 in) standard gauge | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electrification | Third rail | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Operating speed | 80 km/h (50 mph) | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
This Line is divided into two sections; the Eastern section from Suwinthawong - Thailand Cultural Centre (22.5km) and the 2nd phase Western section from Thailand Cultural Centre - Bang Khun Non (17.5 km). Construction of the 22.5km Eastern Section started in June 2017,[2] and the line is scheduled to open in March 2024.[3] On 3 July 2020, the MRTA released the tender for the design and construction of the Western extension.[4]
When fully completed, the MRT Orange line will be 35.9 km long with 29 stations (7 stations will be elevated for 8.9 km and 22 will be underground for 27 km), including an interchange with the current Thailand Cultural Centre Station of MRT Blue Line).
At the end of November 2020, construction had progressed to 72.74%.[5]
Alignment
The MRT Orange Line starts at Suwinthawong rd in Min Buri District in Bangkok's eastern suburbs as an elevated line running along Ramkhamhaeng Road. It will interchange with the future MRT Yellow Line at Lam Sali station. It then proceeds underground near Lam Sali intersection in Bang Kapi District, where there will be a transfer to the MRT Yellow Line. It continues southwest along Ramkhamhaeng Road, passing Hua Mak Stadium and Ramkhamhaeng University to Rama IX rd intersection. The line then proceeds west along Rama IX rd and crosses Pradit Manutham Road to the current Mass Rapid Transit Authority of Thailand (MRTA) Headquarters and MRT Blue line depot. Then it routes north to the Thailand Cultural Centre Station to interchange with the MRT Blue Line.
The western section of the MRT Orange Line, runs west from Thailand Cultural Centre Station via Din Daeng housing estates and Bangkok City Hall 2 to Vibhavadi Rangsit Road, Sam Liam Din Daeng Junction. Then turns left into Ratchaprarop Road towards Pratu Nam and turns right into Phetchaburi Road then interchanges with BTS Sukhumvit Line at Ratchathewi Station. It continues along Lan Luang Road and Ratchadamnoen Avenue, then crosses the Chao Phraya River near Phra Pinklao Bridge, passes Siriraj Hospital and goes along Bangkok Noi Rail line and terminates at Bang Khun Non at Charan Sanitwong rd, where it interchanges with the MRT Blue Line.
History
The original plan of the MRT Orange Line aimed to serve travel demand between the northwestern area of Thonburi, at Bang Bamru Railway Station in Bang Phlat District, and the east of Bangkok in Bang Kapi District. It was planned to run along Ramkhamhaeng Road and Ratchawithi Road, passing many public places like Hua Mak Stadium, Dusit Zoo and Victory Monument, and provide access to universities including Ramkhamhaeng University, Suan Sunandha and Suan Dusit Rajabhat University and many government offices.
In 2009, the proposed MRT Brown line from Bang Kapi District, elevated along Ram Khamhaeng Road, to the eastern suburb in Saphan Sung District and Min Buri District, was merged with the Orange Line in Bangkok's mass rapid transit master plan.[6] In July 2011, the section from Bang Khun Non to Taling Chan was finally scrapped in favour of the SRT Light Red Line spur line which duplicates the same route.[7] In 2012, there were further notable changes made to the central and western sections of the Orange Line. The section from Din Daeng District to Bang Bamru was rerouted away from Victory Monument and Ratchawithi road route to further run south to Pratunam and then west along Petchaburi Road and Larn Luang Road. Continuing farther west along Ratchadamnoen Klang Road and Sanam Luang before passing under the Chao Praya river and finally terminating at Bang Khun Non to interchange with the MRT Blue Line extension.
The MRT Orange line was originally planned to be tendered by the end of 2013. However, due to protests by residents regarding station footprint and compulsory land acquisition around stations at Pratunam, Ratchaprarop, Pracha Songkhro and Soesim stations the MRTA needed another 12 months to redesign sections of the line.[8] Subsequently, political protests against the Thai government led to the metro transport funding bill lapsing when parliament was dissolved in December 2013. On 9 December 2015, Cabinet finally approved the Orange Line.
Construction Progress
On 19 April 2016, the Cabinet further approved a budget of 82.9 billion baht for Phase 1 East section to build 17 stations and 21.2 km of rail from the Thailand Cultural Centre to Minburi, of which 12.2 km will be underground and 9 km will be elevated.[9] Construction contracts were signed on 9 February 2017 between the MRTA and CKST Joint Venture consortium.[10] Construction finally started in June 2017 with a 1980 day construction period with a scheduled opening in October 2022.[11] Project construction is divided into 4 contracts.
As of 31 December 2017, the progress of civil works construction was at 4.66% according to the MRTA.[12] As of July 2018, overall construction progress is at 13.57%. As of August 2018, overall construction progress is at 16.21%.[13] By 30 September 2018, overall construction had progressed to 18.33%.[14] At the end of March 2019, construction has progressed to 32.12%.[15] At the end of July 2019, civil construction was at 42.27%.[16] At the end of October 2019, construction has progressed to 49.05%.[17] At the end of January 2020, construction had progressed to 54.93%.[18] By the end of May 2020, construction had progressed to 62.42%.[19] At the end of July 2020, construction had progressed to 66.06%.[20] On 5 October 2020, TBM number 2 finished tunneling and reached Ramkhamhaeng 12 station box as part of contract 2.[21] At the end of September 2020, was at 69.82%.[22]
At the end of November 2020, construction had progressed to 72.74%.[23]
The eastern section has a planned opening date of March 2024.
Construction contracts
Construction is divided into four separate contracts.
Contract 1 is for 6.29km underground and 4 underground stations from Thai Cultural Centre interchange station to Rankhamhaeng 12 station.
Contract 2 is for 3.44km underground and 4 underground stations from Ramkhamheang 12 station to Hua Mark station.
Contract 3 is for 4.04km underground and 3 underground stations from Hua Mark station to Klong Ban Ma station.
Contract 4 is 8.8km and 7 elevated stations from Klong Ban Ma to Suwinthawong terminus station.[24]
Contract | Notes | Kilometre | Progress (31 November 2020)[25] |
---|---|---|---|
1 | Thailand Cultural Centre to Ramkhamhaeng 12 (4 stations) | 6.29 | 82.52% |
2 | Ramkhamhaeng 12 to Hua Mark (4 stations) | 3.44 | 68.85% |
3 | Hua Mark to Klong Ban Ma (3 stations) | 4.04 | 71.91% |
4 | Klong Ban Ma to Suwinthawong (7 stations) | 8.8 | 61.83% |
5 | Rolling stock | 76.05% | |
6 | Signalling and Electrical | 70.02% | |
Phase 2 Western Extension
The Phase 2 Western extension of the Orange line will run from Thailand Cultural Centre to Bang Khun Non via Pratunam. The 17.5km western section will run underground with 12 stations.
The Thai Cabinet was expected to approve the 121 billion baht budget for the Western extension in mid 2017 with a tender due for the 2nd half of 2017.[26] However, this decision was delayed until 2018 as Cabinet requested options to be considered for a joint public and private investment proposal.[27] There were further delays into 2019, but the MRTA finalised a joint PPP plan for Cabinet to approve in mid 2019.[28] On 28 January 2020, the Cabinet approved the 142 billion baht extension. It is expected to open in February 2026 and serve 439,000 passengers daily.[3][29]
On 3 July 2020, the MRTA released the tender for the design, construction and operation of the Western extension as a Public-Private Partnership project on a 30 year lease.[30] The tender closes on 23 September 2020 with the successful bidder expected to be announced in early October 2020. The tender specifies a construction period of 3 and a half years.
There are 10 tenders that purchased the request for proposal (RFP) form and two rival consortia were submit bids:
- Bangkok Expressway and Metro Public Company Limited (BEM).
- BSR Consortium, led by Bangkok Mass Transit System Public Company Limited (BTSC), and supported by BTS Group Holdings (BTS Group) and Sino-Thai Engineering and Construction (STECON).
Stations
In the table below, an italicised name indicates that the station is not yet in operation.
Code | Station Name | Thai | Interchange | Notes |
---|---|---|---|---|
Thailand Cultural Centre - Suwinthawong (Construction underway) | ||||
OR29 | Yaek Rom Klao | แยกร่มเกล้า | ||
OR28 | Min Buri | มีนบุรี | MRL (under construction) | |
OR27 | Kheha Ramkhamhaeng | เคหะรามคำแหง | ||
OR26 | Wat Bang Pheng | วัดบางเพ็ง | ||
OR25 | Rat Phatthana | ราษฎร์พัฒนา | ||
OR24 | Nom Klao | น้อมเกล้า | ||
OR23 | Sammakon | สัมมากร | ||
OR22 | Khlong Ban Ma | คลองบ้านม้า | Park & Ride service | |
OR21 | Sri Burapha | ศรีบูรพา | ||
OR20 | Yaek Lam Sali | แยกลำสาลี | MRL (under construction)
MRT (design phase) |
|
OR19 | Ramkhamhaeng 34 | รามคำแหง 34 | ||
OR18 | Rajamangala | ราชมังคลา | ||
OR17 | Ramkhamhaeng University | มหาวิทยาลัยรามคำแหง | ||
OR16 | Ramkhamhaeng 12 | รามคำแหง 12 | ||
OR15 | Wat Phra Ram 9 | วัดพระราม 9 | MRL (proposed) | |
OR14 | MRTA | รฟม. | Depot | |
OR13 | Thailand Cultural Centre | ศูนย์วัฒนธรรมแห่งประเทศไทย | MRT | Park & Ride service |
Bang Khun Non - Thailand Cultural Centre (Western Extension) | ||||
OR12 | Pracha Songkhro | ประชาสงเคราะห์ | MRL (planned) | |
OR11 | Din Daeng | ดินแดง | ||
OR10 | Rang Nam | รางน้ำ | ||
OR9 | Ratchaprarop | ราชปรารภ | ARL | |
OR8 | Pratunam | ประตูน้ำ | ||
OR7 | Ratchathewi | ราชเทวี | BTS : Ratchathewi Station | |
OR6 | Yommarat | ยมราช | SRT (Proposed) | |
OR5 | Lan Luang | หลานหลวง | ||
OR4 | Democracy Monument | อนุสาวรีย์ประชาธิปไตย | MRT extension (approved) | |
OR3 | Sanam Luang | สนามหลวง | ||
OR2 | Siriraj | ศิริราช | SRT (Proposed) | |
OR1 | Bang Khun Non | บางขุนนนท์ | MRT SRT (Proposed) |
See also
- Mass Rapid Transit Master Plan in Bangkok Metropolitan Region
- Bangkok Metro
- MRT Blue Line
- MRT Brown Line
- MRT Grey Line
- MRT Light Blue Line
- MRT Pink Line
- MRT Purple Line
- MRT Yellow Line
- BTS Skytrain
- Sukhumvit Line
- Silom Line
- Airport Rail Link (Bangkok)
- SRT Light Red Line
- SRT Dark Red Line
- Bangkok BRT
- BMA Gold Line
References
- "Six contracts signed for construction of B79.2bn Orange Line". Bangkok Post. 9 February 2017.
- "Six contracts signed for construction of B79.2bn Orange Line". Bangkok Post. Retrieved 2017-02-12.
- Theparat, Chatrudee (30 October 2020). "Tangled lines". Bangkok Post. Retrieved 31 October 2020.
- "MRT Orange Line extension tender". MRTA Website. 3 July 2020.
- https://www.facebook.com/MRTA.PR/photos/pcb.2679457458937638/2679457252270992 MRTA Press, 8 December 2020
- "Archived copy". Archived from the original on 2010-06-11. Retrieved 2010-03-17.CS1 maint: archived copy as title (link)
- http://www.manager.co.th/Business/ViewNews.aspx?NewsID=9540000082642
- "Archived copy". Archived from the original on 2014-03-20. Retrieved 2014-03-20.CS1 maint: archived copy as title (link)
- http://www.bangkokpost.com/news/general/939669/orange-line-wins-cabinet-approval
- http://englishnews.thaipbs.or.th/construction-orange-line-contracts-signed. Thai PBS, 9 February 2017
- http://www.bangkokpost.com/news/transport/1287118/lane-closures-for-orange-line-start-in-ramkhamhaeng. Bangkok Post, 14 July 2017
- https://www.mrta.co.th/th/news/information/ความก-าวหน-าการก-อสร-างรถไฟฟ-า-ณ-31-ธ-นวาคม-2560/. MRTA Press, 16 January 2018
- "MRT Orange Line Construction progress". Retrieved 2018-09-11.
- https://www.facebook.com/MRTA.PR/photos/a.1433440196872710/2109998672550189/. MRTA Press, 12 October 2018
- https://www.facebook.com/MRTA.PR/photos/a.1433440196872710/2214355752114480 MRTA Press, 12 April 2019
- https://www.facebook.com/MRTOrangeLineEast/photos/pcb.642832046196150/642831682862853 MRTA Press, 9 August 2019
- https://www.facebook.com/MRTOrangeLineEast/photos/pcb.642832046196150/642831682862853 MRTA Press, 10 November 2019
- https://www.facebook.com/MRTA.PR/photos/a.1409211292628934/2436659376550782 MRTA Press, 7 February 2020
- https://www.facebook.com/MRTOrangeLineEast/photos/pcb.868116043667748/868111270334892 MRTA Press, 5 June 2020
- https://www.facebook.com/MRTA.PR/photos/pcb.2574152359468149/2574151689468216 MRTA Press, 5 August 2020
- https://www.facebook.com/watch/?v=262457361675721 MAA Consultants Co Ltd, 6 October 2020
- https://www.facebook.com/MRTA.PR/photos/pcb.2627818000768251/2627816464101738 MRTA Press, 8 October 2020
- https://www.facebook.com/MRTA.PR/photos/pcb.2679457458937638/2679457252270992 MRTA Press, 8 December 2020
- http://thailand.ahk.de/fileadmin/ahk_thailand/Business/biddingannouncements/MRTA.pdf. MRTA Tender Invitation, 29 June 2016
- https://www.facebook.com/MRTA.PR/photos/pcb.2679457458937638/2679457345604316/
- "B385bn Rail Projects expected to go ahead". Bangkok Post. 26 May 2017.
- "Ministry mulls Orange Line cost transfer". Bangkok Post. 15 August 2017.
- "B230bn for Orange Line". Bangkok Post. 7 May 2019.
- "MRT extension approved". Bangkok Post. 29 January 2020.
- "MRT Orange Line extension tender". MRTA Website. 3 July 2020.
External links
Wikimedia Commons has media related to MRT Orange Line. |