U.S. Geothermal
U.S. Geothermal, Inc. was an independent geothermal energy company focused on the development, production and sale of electricity from geothermal energy, until its acquisition by Ormat Technologies in January 2018.[1] The company operates three geothermal plants in the United States.[2][3] located in Idaho, Oregon and Nevada, and is developing power plants in California, Nevada, Oregon as well as in Central America in the Republic of Guatemala.[4]
Type | Public |
---|---|
AMEX: HTM | |
Industry | Renewable Energy |
Founded | 2000 |
Headquarters | Boise, Idaho, United States |
Website | www |
Existing operations
Neal Hot Springs
U.S. Geothermal’s flagship project and Oregon’s first commercial Geothermal power plant. It came on-line in November 2012.
Equity Partner: Enbridge (40%), $36 B Energy Pipeline Co.
Project Loan: Lender - U.S Dept. of Energy, Fixed 2.6% APR, 22-year term, $61.8 M balance (2/29/16), 60% USG / 40% Enbridge.
Power Sales Contract: Idaho Power Company, 25-year term, Contract Average Energy Price $126.36 per megawatt-hour.
22 net MW (annual average): Air Cooled, 30 MW (winter), 14 MW (summer).
High Reliability: Availability 2015 average 97.9% (excluding schedule annual overhaul).
San Emidio Power Plant
Near-Term expansion opportunity, went on-line in May 2012.
Equity Partner: None.
Project Loan: Lender - Prudential Insurance, Fixed 6.75% APR, 24-year term, $29.7 million balance (2/29/16).
Power Sales Contract: NV Energy, 25-year term, Contract Average Energy Price $103.52 per megawatt-hour.
10 net MW (annual average): Water Cooled.
High Reliability: Availability 2015 average 98.6% (excluding schedule annual overhaul).
Raft River Power Plant
Pacific Northwest and Idaho’s first Geothermal power plant. It went on-line in January 2008.
Equity Partner: Goldman Sachs (5%), Tax equity ownership structure.
Project Loan: None.
Power Sales Contract: Idaho Power Company, 25-year term, Contract Average Energy Price $66.22 per megawatt-hour, Contract Average REC price $7.10.
13 net MW (annual average): Water Cooled, 10 MW current production.
High Reliability: Availability 2015 average 95.4% (excluding schedule annual overhaul)
Development Projects
Advanced development projects near term expectations:
WGP Geysers Project - California
Expected plant size 30 MW net. Expected on-line date - 2018. Expected cost to build $150 M. Qualified for 30% investment tax credit. Status – 5 wells drilled with 30 MW of steam currently available for production.
El Ceibillo - Guatemala
Expected plant size 25 MW net. Expected on-line date (phase 1) - 2018. Expected cost to build (phase 1) $140 M. Qualified for 10 year income tax holiday. Status – production well drilling in progress.
San Emidio II - Nevada
Expected plant size 10 MW net. Expected on-line date (phase 2) - 2017. Expected cost to build (phase 2) $60 M. Qualified for 30% investment tax credit. Status – production well drilling in progress.
Crescent Valley - Nevada
Expected plant size (phase 1) 25 MW net. Expected on-line date (phase 1) - 2018. Expected cost to build (phase 1) $130 M. Qualified for 30% investment tax credit. Status – first well completed with additional drilling in planning.
Key management
Dennis Gilles, CEO
Board Member U.S. Geothermal since 2011. Previous SVP of Calpine, prior experience at SCE/Mission and BP/ARCO. Engineer & MBA, 35 years energy management experience, 29 years in geothermal.
Doug Glaspey, President & COO
Co-founder of U.S. Geothermal, Engineer with 37 years in natural resource exploration, development and operation, including 13 years of geothermal experience.
References
- Notes
- "U.S. Geothermal Inc. Enters Into Definitive Agreement to Be Acquired by Ormat Technologies Inc. for $5.45 in Cash Per Share". January 24, 2018. Retrieved April 23, 2019.
- "Profile: U.S. Geothermal Inc". Yahoo! Finance. 2015. Retrieved November 17, 2015.
- "U.S. Geothermal Provides Company Update". The Wall Street Journal. January 13, 2014. Retrieved February 25, 2014.
- "US Geothermal Inc: NYSEMKT:HTM quotes & news". Google Finance. 2015. Retrieved November 17, 2015.