Askam and Ireleth Wind Farm

Askam and Ireleth Wind Farm is a group of 7 turbines located two kilometers east of the village Askam and Ireleth, on the southern slopes of Hare Slack Hill. Work on the turbines started in late 1998, and the wind farm took eight months to complete. It first generated energy in July, 1999.[1]

Askam and Ireleth Wind Farm
CountryEngland, United Kingdom
LocationAskam and Ireleth
Coordinates54°11′14″N 03°10′20″W
StatusOperational
Construction began1998
Commission dateJuly 1999
Operator(s)B9 Energy
Wind farm
Type
Power generation
Units operational7 x 0.66 MW
Make and modelVestas: V47
Nameplate capacity4.62 MW
Some of the wind turbines.

Description

Recent reports show the windfarm is producing only 30.2% of the theoretical maximum amount of electricity claimed by then-operators Powergen in the planning application.[2]

E.ON, developer and owner, claims that the wind farm generated enough renewable electricity in 2005 to supply nearly 2,500 homes and avoided the emission of over 4,000 tonnes of carbon dioxide.[3] The wind farm, which features seven turbines measuring 40 metres (131 ft) to the top of the tower, is not permanently manned. Instead it is controlled and monitored from Rheidol Hydroelectric Power Station, near Aberystwyth, Mid Wales.[4]

Local opposition to the windfarm

The Marton, Askam and Ireleth Windfarm Action Group (MAIWAG) was formed by local residents of the three villages upset by what they saw as the inconsiderate construction of the windfarm by then developers Wind Prospect. The group claimed the reality of the windfarm at Far Old Park farm bore little resemblance to the proposed scheme they were first told about.[5] Their main concerns related to the size and environmental impact of the development as well as noise it produced. It was discovered that six of the seven turbines were not constructed in line with the developer's original application and as such did not have planning permission.[6] Barrow Borough Council signed an agreement with the developer, imposing a range of planning conditions on the turbines already built. As complaints by local residents continued to be made about the noise the council resolved to take action against the windfarm. Later, borough councillors decided to drop this planned enforcement action in December 2002. Disappointed by this decision, six members of the group went ahead with a private prosecution against the owners and operators of the windfarm on the grounds it was a "noise nuisance". But their case was unsuccessful.[7]

Members of the group later toured the country to share their experiences and aid other countryside defence groups in their fight against excessive windfarm development.[8]

References

  1. "Askam". B9 Energy. Archived from the original on March 4, 2007. Retrieved 2007-03-10.
  2. Hall, Dr Mike. "Wind Energy – Saint or Sinner? [page 3 of 5]" (PDF). The Scottish Parliament. Retrieved 2007-03-10.
  3. "E.ON UK – Askam". E.ON. Archived from the original on 2006-10-29. Retrieved 2007-07-24.
  4. "Askam". E.ON UK. Archived from the original on 2007-03-02. Retrieved 2007-03-10.
  5. "Broken Promises". MAIWAG. 2004. Archived from the original on October 8, 2007. Retrieved 2007-04-15.
  6. "Noise Windfarms Court Battle" (doc). MAIWAG. Retrieved 2007-04-15.
  7. "Judge rejects wind farm complaint". BBC. 2004-01-20. Retrieved 2007-03-10.
  8. "David Brierley presentation". Stop Cambridge Windfarm. Archived from the original on 2 May 2007. Retrieved 2007-04-15.
This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.