Goupitan Dam

The Goupitan Dam (simplified Chinese: 构皮滩大坝; traditional Chinese: 構皮灘大壩; pinyin: Gòupítān Dàbà) is an arch dam on the Wu River, a tributary of the Yangtze River in Guizhou Province, southwest of China. The dam's hydroelectric facility will operate on five turbines, each with a hydroelectric generating capacity of 600 MW, for a total of 3,000 MW. Constructions began on in 2003 and the first generator was operational in June 2009.[1] All works were completed in 2011.[2][3][4]

Goupitan Dam
Location of Goupitan Dam in China
Official name构皮滩大坝
LocationGuizhou, China
Coordinates27°22′31″N 107°37′59″E
StatusOperational
Construction beganNovember 2003
Opening date2009
Construction cost¥13.842 billion
Dam and spillways
Type of damDouble-curvature arch dam
ImpoundsWu River
Height232.5 m (763 ft)
Length557.11 m (1,828 ft)
Reservoir
CreatesGoupitan Reservoir
Total capacity6,451,000,000 m3 (5,229,911 acre⋅ft)
Catchment area43,250 km2 (16,699 sq mi)
Surface area94.29 km2 (36 sq mi)
Power Station
Commission date2009
Turbines5 × 600MW
Installed capacity3,000 MW
Annual generation9.667 TWh (est.)

Xinhua reported, on July 3, 2020, that the dam would be complete by March 2021.[5]

The dam is supplemented by the Goupitan shiplift, said to be the tallest shiplift in the world.[6]

See also

References

  1. "Goupitan Hydropower Station" (in Chinese). Eighth China Water Conservancy and Hydropower Engineering Bureau, Ltd. Retrieved 26 September 2011.
  2. Goupitan Hydropower Project (PDF), Chinese National Committee on Large Dams, archived from the original (PDF) on 2014-04-16, retrieved 2010-03-12
  3. "构皮滩水电站工程情况简介_网易新闻中心". Archived from the original on 2006-09-02. Retrieved 2008-02-09.
  4. "四在农家――余庆". Archived from the original on 2011-07-20. Retrieved 2008-02-09.
  5. "View of Goupitan hydropower station in Yuqing County, Guizhou". Xinhua. 2020-07-03. Archived from the original on 2020-10-13. Aerial photo taken on July 2, 2020 shows the vertical ship lift at the Goupitan hydropower station in Yuqing County, southwest China's Guizhou Province. Goupitan hydropower station navigation project is scheduled to be put into use in March, 2021.
  6. "Redaelli supplies the steel wire ropes for the tallest shiplift in the world". Redaelli. 2016-12-12. Archived from the original on 2018-09-13. Retrieved 2018-09-12. By mean of this ship-lift a water level difference of 199 meters is overcome by mean of 3 stage of lifting, the 2nd stage alone being 127 meters, more than the overall high of the Three Gorges dam.


This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.