Parli Thermal Power Station
Parali Thermal Power Plant is located at Parali Vaijnath in Beed district of Maharashtra. The power plant is one of the coal based power plants of Maharashtra State Power Generation Company (Mahagenco).[1]
Parali Thermal Power Station | |
---|---|
Country | India |
Location | Parali, Beed, Maharashtra |
Coordinates | 18.868768°N 76.526127°E |
Status | Operational |
Commission date | 1971 |
Operator(s) | Maharashtra State Power Generation Company (Mahagenco) |
Thermal power station | |
Primary fuel | Coal |
Power generation | |
Units operational | 6 |
Nameplate capacity | 1380.00 MW |
External links | |
Website | mahagenco |
Installed Capacity
Stage | Unit Number | Installed Capacity (MW) | Date of Commissioning | Status |
---|---|---|---|---|
Stage I | 1 | 30 | 1970 August | Abandoned |
Stage I | 2 | 30 | 1971 March | Abandoned. |
Stage II | 3 | 210 | 1979 April | Abandoned. |
Stage II | 4 | 210 | 1980 July | Running. |
Stage II | 5 | 210 | 1981 January | Running. |
Stage III | 6 | 250 | 2007 | Running. |
Stage III | 7 | 250 | 2010 | Running. |
Stage III | 8 | 250 | 2016 | Running.[2] |